Country Client Year Project Scope Details
KSA Hyundai Heavy Ind. 2015-2016 South Jeddah (4*660)MW Oil Fired - Thermal Plant Supercritical Staffing for plants operation
EGYPT AC Boilers 2015 Suez Thermal Power Plant 1x650MW Mechanical Commissioning and Operation
EGYPT General Electric 2015 TM2500+™ Mobile Gas Turbine Generators at 10 sites each with 2 units Staffing for plants operation
EGYPT General Electric 2015 Assiut 8X125MW W. Damietta 4X125MW Staffing for plant commissioning and operation
EGYPT Electro Tharwat 2015 Assiut 8X125MW W. Damietta 4X125MW Testing and Commissioning of GCB, UAT, GSUT and IPB.
EGYPT GE / TSK / Hassan Allam Construction 2015 14 Gas Turbine LM 6000 at three sites Hurgada , Sharm Elshiekh and port said Pre commissioning and flushing of 14 Gas turbine LM6000.
EGYPT General Electric 2015 Kuraimat Solar 150MW ISCC Manpower for outage for turbine shaft maintenance
EGYPT ANSALDO CALDAEI 2014 Banha Power Plant 750MW CCPP HRSG commissioning and operation
KSA HANWHA 2014 Marafiq Yanbu 5&6 Project, Saudi Arabia Providing case study and issuing of Tuning Assessment Report Yanbu Unit #5
KSA SAMSUNG C&T CORPORATION 2013 Qurayyah Independent Power Project (QIPP) 6 x 750MW Commissioning of 6 Combined Cycle Modules (2x2x1)
EGYPT DOOSAN HEAVY INDUSTRIES& CONSTRUCTIONS CO. LTD 2013 Ain Sokhna Power Plant (2X650)MW CP-105 Assist in the Commissioning of 2x650MW Boilers
EGYPT ALSTOM GRID 2013 Giza North PP 2X750MW(500/220 KV SWYRD) Alstom Test. & Comm. of SWYRD & Remote End Prot. Sys.
EGYPT AREVA T&D 2010-2011 El-Mashtal GIS S/S, 66/11 kV - AREVA Test. &Comm. of Sub St. & TL Remote End Prot. Sys.
EGYPT HYOSUNG 2011-2012 Damietta SWYRD, 220KV - HYOSUNG GIS Substation Test. &Comm. of SWY & Remote End Prot. Sys.- Relays setting Calc. Construction supervision
EGYPT ANSALDO ENERGIA 2011-2012 6th Of October Power Plant 4x150 MW Commissioning, Start-up 4 × 150 MW Simple Cycle & Test. &Comm. of SWYRD & Remote End Prot. Sys.
EGYPT ANSALDO CALDAEI 2011-2012 Abu Qir 2x650MW Boilers Commissioning, Start-up and Operation 2x650MW Boilers till handing over
IRAQ ABB Mannheim 2011-2012 - IRAQ Erbil 2x125MW GE Gas T.
- IRAQ - Dohuk4x125MW GE Gas T.
- IRAQ - Al-Solaimanyah 4x125MW GE Gas T
Construction Supervision Commissioning and Start-up of GT & auxiliaries through a seconded commissioning manager GE Gas Turbine
EGYPT AREVA T&D 2010-2011 Bahteem GIS S/S 220/66/11 kV, AREVA Test. &Comm. of Sub St. & TL Remote End Prot. Sys.
EGYPT NEM Energy B.V. 2010-2011 SidiKrir and El-Atf Combined Cycle Power Plant - 750MW each. HRSG systems Commissioning & Operation until handing over to Owner.
EGYPT Toyota Tsusho C. Toshiba Plant Systems & Services C. 2009 SidiKrir and El-Atf Combined Cycle Power Plant - 750MW each Preparation of Chemical cleaning procedure for the Condensate and Feed Water System.
EGYPT Toyota Tsusho C. Toshiba Plant Systems & Services C.(TPSC) 2009-2013 El-Atf Simple Cycle Power Plant - 750MW Lump Sum Contract Commissioning of the Electrical and Mechanical BOP and related services.
EGYPT Toyota TC/ Toshiba (TPSC) 2009-2013 Sidi Krir Simple Cycle Power Plant - 750MW CP-118 & CP-117 Assist in the commissioning of Mechanical BOP and related services.
EGYPT Mitsubishi Electric Co. (MELCO) 2009 SidiKrir Simple Cycle Power Plant - 750MW CP-101 Long Term Service Agreement for Commissioning and Support and Start-up Activities
QATAR ABB Mannheim 2009 QATAR - QATALUM Combined Cycle Power Plant POB Construction and Commissioning Management
QATAR ABB Manheim 2007-2008 QATAR - Abu Fontas Power Plant Project (QEWC) – Qatar POB Construction and Commissioning Management
LIBYA ABB Manheim 2006 LIBYA - Benghazi 319 pumping station Electrical Systems installations supervision, commissioning and startup services.
EGYPT ALSTOM Power Inc. 2001-2003 Aswan High Dam Control System Upgrade 12x175MW Commissioning and start- up of Aswan High dam new DCS system.